Please use this identifier to cite or link to this item: http://repositorio.lnec.pt:8080/jspui/handle/123456789/1017580
Full metadata record
DC FieldValueLanguage
dc.contributor.authorBrito, A.pt_BR
dc.contributor.authorCarreto, J.pt_BR
dc.contributor.editorNuno Guerrapt_BR
dc.contributor.editorManuel Matos Fernandespt_BR
dc.contributor.editorCristiana Ferreirapt_BR
dc.contributor.editorAntónio Gomes Correiapt_BR
dc.contributor.editorAlexandre Pintopt_BR
dc.contributor.editorPedro Sêco e Pintopt_BR
dc.date.accessioned2024-09-16T15:03:34Zpt_BR
dc.date.accessioned2024-10-07T15:28:25Z-
dc.date.available2024-09-16T15:03:34Zpt_BR
dc.date.available2024-10-07T15:28:25Z-
dc.date.issued2024-08pt_BR
dc.identifier.citation10.1201/9781003431749pt_BR
dc.identifier.urihttp://repositorio.lnec.pt:8080/jspui/handle/123456789/1017580-
dc.description.abstractFor World Youth Day event in 2023 (JMJ), the organizing committee selected an area in Parque das Nações that met the imposed requirements, notably in terms of area (for 1 million spectators) and proximity to the Lisbon center. This area, on the other hand, has the distinction of being a sanitary landfill, which was sealed in 1997 as part of the EXPO98 interventions, and which previously, in 1995, experienced a large-scale landslide in the direction of the river, with a front of 300 m of extension, enveloping the foundation up to significant depths. The fundamental cause of the landslide, according to studies undertaken at the time, was the low undrained strength of the foundation's soft soils that were still in the subconsolidation phase, particularly at the deepest levels. Considering this scenario, LNEC performed limit equilibrium stability analyses as well as three-dimensional stress and strain finite-element analyses to estimate the magnitude and evolution of the settlements of the JMJ stage to be built in the southern area. The analyses carried out, the results of which are presented in the article, revealed the need of a pre-load embankment and were used to define criteria for the constructive phasing of the work, which was inherently dynamic and based on the outcomes of the monitoring system installed on site. Finally, values obtained from the monitoring system installed during the construction phase are compared to the values estimated during the design phase.pt_BR
dc.language.isoengpt_BR
dc.publisherCRC Presspt_BR
dc.rightsrestrictedAccesspt_BR
dc.subjectSanitary landfillpt_BR
dc.subjectpre-load embankmentpt_BR
dc.subjectsoft soilspt_BR
dc.subjectslope stabilitypt_BR
dc.subjectconsolidationpt_BR
dc.titleDesigning a pre-load embankment for the construction of a stage over a sanitary landfill founded in soft soilspt_BR
dc.typeworkingPaperpt_BR
dc.identifier.localedicaoLisbonpt_BR
dc.description.pages6p.pt_BR
dc.description.commentsThe authors are grateful to Lisboa Ocidental SRU - Sociedade de Reabilitação Urbana E.M., S.A. for granting permission to disseminate the study's findings.pt_BR
dc.identifier.localLisbonpt_BR
dc.description.sectorDG/NGUTpt_BR
dc.description.magazineGeotechnical Engineering Challenges to Meet Current and Emerging Needs of Societypt_BR
dc.identifier.conftitleXVIII European Conference on Soil Mechanics and Geotechnical Engineeringpt_BR
dc.contributor.peer-reviewedSIMpt_BR
dc.contributor.academicresearchersNAOpt_BR
dc.contributor.arquivoNAOpt_BR
Appears in Collections:DG/NGOH - Comunicações a congressos e artigos de revista

Files in This Item:
There are no files associated with this item.


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.